Blanca City Vung Tau Construction Progress September 2026: Coastal Urban Area Taking Shape
The construction progress of Blanca City Vung Tau records remarkable milestones across high-rise, low-rise residences, and internal road infrastructure. The Beacon Tower and Beachtro Tower twin complex has completed 100% of the B3 basement concrete floor and is expediting the B2 level structure, while Casa villas advance rapidly toward on-schedule delivery in late 2026.
From foundational works on the major 3rd February frontage corridor, Blanca City is step by step defining the stature of an elite coastal urban district at Bai Sau. Below is an exhaustive structural evaluation based on actual site conditions.
Beacon Tower and Beachtro Tower: Continuing Basement Concrete Slabs
The long-term ownership twin residential towers, Beacon Tower and Beachtro Tower, are concurrently progressing through technical basement slab fabrication. Deep foundational piles and retaining walls have passed strict structural acceptance inspections, ensuring optimal load-bearing conditions for coastal high-rise engineering.
Technical Element
Beachtro Tower
Beacon Tower
Construction Status
B3 Basement Floor
100%
100%
Load-bearing tests successfully passed
B2 Basement Floor
25%
70%
Second pour section underway
B1 Basement Floor
25%
25%
Formwork and rebar installation active
Real site status of B3 slab pouring and B2 structural walls across Beacon Tower and Beachtro Tower.
Reaching 70% of the B2 basement floor at Beacon Tower provides solid groundwork for topping out the entire subterranean structure next quarter, paving the way for above-ground framing at an estimated speed of 3 levels per month.
Blanca Tower Precinct: 100% Foundation Concrete Accomplished
At Blanca Tower precinct, foundation and tie-beam concrete fabrication has attained 100% completion. Civil contractors are mobilizing heavy machinery to proceed with extended underground works.
All foundational segments of Blanca Tower have received regulatory sign-off.
Sub-zones B1, B2, and B3 completed 100% of blinding concrete.
Casa Villas Zone: Outer Walls Framing and Preparing Handover
The single and semi-detached Casa villa residences demonstrate outstanding construction velocity. Exterior brick wall construction and rough facade finishing are accelerated to target handover by late October 2026.
Villa Segment
Outer Walls (%)
Structural Finish (%)
Handover Timeline
Casa Detached Block A
95%
88%
Expected October 2026
Casa Semi-Detached Block B
90%
80%
Expected November 2026
Beachfront Boutique Villa
100% piles
60% basement structure
On scheduled track
The detached Casa villas have accomplished most outer brickwork and structural facade glazing profiles.
The Beachfront Boutique Villa precinct has completed deep foundation engineering and is progressing with basement structural fabrication, protecting beachfront privacy and panoramic ocean vistas.
Internal Traffic Grid and Public Amenities
Civil infrastructure across Blanca City has achieved pivotal milestones, establishing conditions for synchronized operation upon residential delivery.
Internal asphalt road networks for phase 1 reached 92%.
Medium-voltage underground conduit and substation systems achieved 95% volume.
From a capital management standpoint, closing the subterranean phase signifies that official sales contracts will be signed shortly. Investors leveraging bank interest subsidies should observe: